Oversized Elevators |
|
Management of Construction |
|
$0 |
|
Elevator |
|
NA |
|
10-1-1282 |
|
State / Municipal Government |
|
14 |
|
|
|
|
|
Southeast |
|
An oversized elevator had to be installed for delivery of the (client’s) current and future artifacts. |
|
|
|
Being the biggest elevator in the county, the installation crew underestimated the length of time and the
complexities associated with assembling the elevator. The elevator took considerably longer to install than
anticipated. |
|
|
|
Particular attention should be given to the construction of this elevator as it was scheduled to be complete in 8 weeks and it took approximately 16 additional weeks to be operational. Review the elevator manufacturer
requirements, obtain early approvals and fabrication release. Begin construction of the elevator as early as possible. |
|
|
Updated: 05/2010 |
|
|
 |
 |
 |
 |
 |